Arbedo-Castione, 2014

Ponte Moesa Arbedo-Castione

Project overview

In two stages, Itenbau AG carried out the sliding-out of the existing 1,720-tonne bridge and the sliding-in of the new 1,340-tonne bridge by 10 metres each.

Challenges

Both sliding operations were accomplished with one system.